Wilkes Ave Public Domain Upgrade

Update September 10, 2021 – Council is hoping to have the new lighting installed in Wilkes Ave in October.

April 24, 2021 – Construction of one side of the raised wombat crossing has been delayed due to unexpected sewerage & telecommunication services located underground and weather. Once complete, hopefully in the next 1-2 weeks, work will commence on the other half of the road (to complete the wombat crossing).

January 23rd, 2021 – starting with the construction of a raised pedestrian crossing on Elizabeth Street (approx. 3 months of work) followed by streetscape improvements to Wilkes Avenue plaza including installation of new street furniture and decorative lighting (approx. 2 months of work). The Artarmon Progress Association (APA) submission can be found HERE